The following milestones were defined to keep track on the experiment progress and define the products of the experiment.

Milestones:

M1 (Q1 2018): Finalise design

M2 (Q1 2019): experiment emplaced and non-active circulation started

M3 (Q1 2020): start of circulation of radionuclides

M4 (Q1 2022): Decision to overcore and distribute samples to laboratories or to continue circulation

M5 (End 2022): end of the first phase of the CIM project

 

Fig 3 Current project organisation

Figure 3: Current project organisation- Organisation