The working programme comprises of the following steps:
Step 1: Finalise experimental design
Step 2: Drill needed boreholes and install initial condition monitoring
Step 3: Develop and construct the experimental equipment (packer system, surface equipment)
Step 4: Emplace circulation interval
Step 5: Start circulation and monitoring
Step 6: Overcore and post-mortem analysis
The project relies largely on experience acquired with previous projects using radionuclides at GTS (LTD, CFM) and will benefit from the lessons learned of these projects with respect to borehole and surface equipment and sampling.