The following milestones were defined to keep track on the experiment progress and define the products of the experiment.
Milestones:
M1 (Q1 2018): Finalise design
M2 (Q1 2019): experiment emplaced and non-active circulation started
M3 (Q1 2020): start of circulation of radionuclides
M4 (Q1 2022): Decision to overcore and distribute samples to laboratories or to continue circulation
M5 (End 2022): end of the first phase of the CIM project
Figure 3: Current project organisation- Organisation