The project is organised in yearly successive project phases. Each phase has been contracted and executed separately. Nagra concludes each phase with a progress report in which the on-site activities and results of the laboratory tests are summarised.
Project phase
|
Tasks
|
I
|
2007/2008
|
-
Geological mapping and site selection
-
Drilling of four boreholes and installation of hydraulic monitoring systems
-
Geologic and structural characterisation, preliminary structural model
-
Thin section analysis of core samples for mineralogical characterisation
-
Hydrogeologic characterisation of fractures with monopole hydraulic testing
|
II
|
2008/2009
|
-
Drilling of one borehole and installation of hydraulic monitoring systems
-
Hydrogeologic and structural characterisation and update of the structural model
-
Analysis of groundwater chemistry
-
Support of CRIEPI’s demonstration experiments
|
III
|
2009/2010
|
-
Drilling of two boreholes and installation of hydraulic monitoring systems
-
Hydrogeologic and structural characterisation and update of the structural model
-
Support of CRIEPI’s demonstration experiments and characterisation of target fracture zone I
|
IV
|
2010/2011
|
-
Support of CRIEPI’s demonstration experiments and characterisation of target fracture zone II
|
V
|
2011/2012
|
-
Excavation of stabilised target fracture
-
Laboratory analysis of fracture aperture
|
CRIEPI’s Fractured Rock Studies - C-FRS